No final plat shall be approved unless it is possible, without undue delay, to supply the following improvements:
(1)
Monuments of iron pipe, stone or concrete shall be set at street intersections, at alley intersections or at such other points as may be required to make the tracing of the lines shown on the final plan reasonably convenient.
(2)
The subdividers shall install water and sewer mains in such diameter as the city engineering may require. The subdivider shall install necessary fire hydrants as determined by the city engineer.
(3)
The subdivider shall install adequate conduits, drains and provisions for stormwater drainage as may be required and approved by the city engineer.
(4)
All streets and alleys shall be paved in accordance with design and construction requirements established by the city engineer and subject to the approval of the city engineer.
(5)
Sidewalks, curbs and gutter, culverts, bridges and other such necessary improvements shall be constructed by the subdivider in accordance with plans and specifications approved by the city engineer and after construction will be subject to inspection and approval by the city engineer. All required improvements shall be completed in accordance with grades officially established by the city.